Process Control Improvements


Please see below a few examples of the Process Control Improvement projects that we have implemented; 

  • Project - Installation of a vision system
    • Request; A plastic component manufacturer required to reduce the amount of bad product from a machine, the defects were causing losses further down the production chain. A stop gap method was to site a person on the exit of the machine inspecting the product.
    • Study; Proplas installed a camera vision system that could identify the defects automatically, which in turn alerted the operator.
    • Result; The system detected 100% of the defects, the additional person was eliminated and the number of defects being produced dropped due to earlier detection.

 

  • Project - Product heating system
    • Request; A manufacturer required a method of heating an area of product, within a machine where space was limited.
    • Study; Proplas investigated several heating methods, and tested a few on the m/c. The most suitable and efficient proved to be a pair of ceramic infrared elements controlled by optical pyrometers, which we were able to control within the existing machine control PLC.
    • Result; The product is heated to specification and meets quality criteria.   The installation fits easily inside the machine without affecting the current assemblies.

 

  • Project - Position indicators to improve quality
    • Request; A textile business required a method of improving the accuracy of placing a fabric onto a moving shaft.
    • Study; Proplas installed a couple of laser line projectors, that clearly indicated the position, this allowed the operator to verify the position whilst the machine was in motion.
    • Result; The solution proved to be very simple and cheap, and simplified the M.O.W..

 

  • Project - Improved Planned Maintenance system for ISO qualification
    • Request; A plastic component manufacturer required to enhance the Planned Maintenance function, to achieve ISO accreditation.
    • Study; Proplas worked with the existing engineers to determine the best solution. We purchased an "off the shelf" package and entered all the information required to produce the necessary documentation; Work orders, Planning's, etc...
    • Result; The PM system meets the ISO standards. The ownership of the plan remains with the engineers through the involvement at the development stage.

 

  • Project - Improving the output of manufacturing unit
    • Request; A manufacturer required a large production unit to improve its output rate. Investment had been substantial in an effort to achieve better results, but they had only moderate improvements that put the plants viability into doubt.
    • Study; Proplas worked with the company for six months which enabled us to fully understand the problems, during this period we made many changes;
      • Simplification of the system, automating several functions
      • Radically changed the scrap re-work method
      • Removal of redundant plant, to improve reliability.
      • Improved the operator interface
    • Result; The output rate has increased by 40% and the product quality is uniform. MTBF improvement - was 48 hours now 2 hours. The unit is still economically in production

 
 